Method Statement for Trench Excavation and Backfill for Electrical Cables

Last updated on: January 23, 2023

Method Statement for Trench Excavation and Backfill for Underground Electrical Cables Laying

In this Article today we will talk about the Method Statement for Trench Excavation | Safe Work Procedure for Trench Excavation | Method Statement for Excavation and Backfilling | Method Statement for Excavation Works pdf | Excavation Methodology | Trenches and Excavations | Underground Cable Installation Method | Excavation SWMS | Excavator Safe Work Method Statement

Method Statement for Trench Excavation and Backfill for Electrical Cables:

Introduction:

The objective of the method statement is to outline the efficient and safe method of work to follow in order to safely and efficiently complete the Trench Excavation & Backfill for Electrical underground Cable Laying and precautionary measures taken to protect workers and existing facilities.

Scope of Work:

The purpose of this method statement is to describe the procedure for the Method Statement for Trench Excavation & Backfill for Electrical underground Cable Laying.

Tools and Equipments:

  • Excavation Hand Tools (08 Nos)
  • Compactor (01 No) Safe Work Procedure for Trench Excavation

Specific Identified Residual Hazards:

  • Working at Trench
  • Dust Method Statement for Excavation and Backfilling

Specific Staff Training Requirements:

Prior to start of the works all persons involved in the activity will be briefed on the content of this Method Statement. Method Statement for Excavation Works pdf

Work Methodology:

Method Statement for Trench Excavation, Safe Work Procedure for Trench Excavation, Method Statement for Excavation and Backfilling, Method Statement for Excavation Works pdf, Excavation Methodology, Trenches and Excavations, Underground Cable Installation Method, Excavation SWMS, Excavator Safe Work Method Statement, method statement for excavation works pdf, method statement and risk assessment for excavation, method statement for excavation and backfilling pdf, excavation safe work method statement, safe work procedure for excavation pdf, method statement for excavation and backfilling, method statement for excavation of foundation, excavation methodology pdf, construction method statement for excavation pdf, trench electric, cable installation, underground cable installation, underground cable laying, electrical trench, cable installation methods, work method statement for construction works, method of work statement, excavation work, risk assessment and method statement, method of statement for electrical works, excavation work, trench and excavation, excavation risk assessment pdf, excavation risk assessment, trench excavation, trench digging, risk assessment method, process of risk assessment, safe excavation, risk assessment method statement, excavation risks, risk assessment for safety, electrical risk assessment, electrical risk, trench backfill, cable trench,
Method Statement for Trench Excavation and Backfill for Electrical Cables
  • Permit to work shall be raised for excavation clearly mentioning the location of work, size of excavation and levels
  • Excavation area shall be surveyed and marked to the lines and levels as shown on the drawings. Excavation Methodology
  • The area of excavation will be cordoned off using barricading to stop trespassers.
  • Required sign boards such as “Deep excavation” “MEN WORKING” “DANGER” and warning boards will be placed to indicate the excavation work.
  • If needed, Proper temporary supports shall be provided to the adjacent structure prior to start excavation. Excavation Methodology
  • Check the area of excavation to find out any underground facilities other than listed in as built drawing by using appropriate equipment such as cable detector, metal detector and trail/test pits to find out existing underground pipes, structures.
  • Excavation near existing utilities (electrical cables, pipes etc.) shall take all necessary precautions to protect the service with proper supports and cover.
  • Manual excavation shall be carried for trench and trial pits.
  • Trench shall be excavated by using hand tools as per marking and levels with proper protection of sides. If Excavation depth exceeds 1.2 m, proper shoring should be provided on sides of trench. Trenches and Excavations
  • The bottom of trench shall be levelled and well compacted.
  • Excavated materials shall be removed, stockpiled or deposited away from the excavation area for reuse or dispose in the approved dumping area as directed by PMCM.
  • 150mm sand bedding shall be done at bottom of trench prior to the installation of cable. Trenches and Excavations
  • Cable shall be laid over sand bedding.
  • 300mm sand layer shall be laid over cable.
  • Cable protection tiles shall be laid over sand layer.
  • Excavated soil shall be backfilled for thickness of 150mm per layer above the cable protection tiles. Stones and boulder shall be avoided from mixing with backfill soil.
  • Each backfill layer shall be well compacted and FDT test shall be conducted for compaction.
  • Install cable warning tape at height of 250mm from top of cable protection tiles.

Inspection Hold Points:

FDT Testing Shall be witnessed by Consultant. Excavator Safe Work Method Statement

Monitoring and Compliance:

  • A Supervisor and HSE officer will be monitoring the activity at all times.
  • Supervisor will ensure that the RAMS are communicated to the operatives prior to commencement of the activity.
  • Start briefing will be conducted and communicated to the operative. HSE Officer will ensure that all required documents are valid and available. 3rd party certificates for equipment, inspection on safety equipment and verify require training of employees
  • Prior to start activity work permit to issue and approved by all relevant parties.

Access and Egress to Testing AREAS:

Access and egress to the working areas will be as follows:

  • Designated working areas to be identified and barricaded. Approved signage (e.g.: ear protect, dust mask, slipping hazard, falling object etc.) Shall be followed in the working location. Access will be provided as per parcel availability.

Fall Protection Measure:

  • Full body harness will be used during activity and anchored points (LANYARD) will be attached to the scaffolding at all times during the activity. Excavation SWMS

Required PPE:

  • Head Protection (Hard hat)
  • Hand protection (Hand gloves)
  • Foot protection (Safety Shoes)
  • High visibility Vest
  • Face Mask. Excavation SWMS
  • Eye Protection (Safety Googles)

Emergency Procedures & Arrangements:

In case of any Emergency, emergency arrangements will be carries out in accordance with the Emergency Response Plan Underground Cable Installation Method


OTHER POSTS:

  1. Method Statement of Polyurethane Waterproofing for Walls and Roof

  2. Method Statement for Cutting and Patching Works

  3. Thumb Rules for Civil Engineering
  4. Bituminous Damp Proofing for Concrete and Masonry | SWMS

  5. How to Calculate Deflection Angle in Surveying

Conclusion:

Full article on Method Statement for Trench Excavation | Safe Work Procedure for Trench Excavation | Method Statement for Excavation and Backfilling | Method Statement for Excavation Works pdf | Excavation Methodology | Trenches and Excavations | Underground Cable Installation Method | Excavation SWMS | Excavator Safe Work Method Statement. Thank you for the full reading of this article in “QA QC in Construction” platform in English. If you find this post helpful, then help others by sharing it on social media. Please share this article on social media for future uses.